Title: Cargill High River Fluidized Bed Boiler Offset Project Project Identifier: 9327-1871

Project Description

The Offset Project results from the implementation of a fluidized bed boiler (FBB) fuelled by biomass sourced from bovine by-products and other compostable plant wastes including meat, pen manure, paunch, dissolved air flotation (DAF) grit, sludge, tricanter solids, and specified risk materials (SRM). The FBB will displace a portion of the natural gas used for process steam requirements and fossil fuel generated electricity through on-site generation at the Cargill High River Beef Processing Plant.

Project Files

Alberta - Project Plan (Project #9327-1871)
Alberta - Project Report (2013 - 2014)
Alberta - Verification Report (2013 - 2014)
Alberta - GHG Assertion (2013 - 2014)
Alberta - GHG Assertion (2013 - 2014) Updated 2016
Alberta - Verification Report (2013 - 2014) Updated 2016
Alberta - Notice of Removal (2013 - 2014)
Alberta - Project Plan (Project #9327-1871) Updated 2016
Alberta - Project Report (2015)
Alberta - Verification Report (2015)
Alberta - GHG Assertion (2015)
Alberta - Offset Project Report (2016)
Alberta - Verification Report (2016)
Alberta - GHG Assertion (2016)
Alberta - Offset Project Report (2017)
Alberta - Verification Report (2017)
Alberta - Project Plan (Project #9327-1871 Updated 2019)
Alberta - Offset Project Report (2018)
Alberta - Verification Report (2018)
Registry: Alberta Emissions Offset Registry Type: Biomass Energy
Quantification Protocol: Energy Generation From the Combustion of Biomass Waste Status: Active
Authorized Project Contact: Blue Source Canada ULC
Latitude: 50.572837   Map
Validator: None defined Longitude: -113.829991
Verifier:
Keystone Environmental
ClearSky Engineering Inc.
Emission Offset Project Developer: Cargill Ltd.
Start Date: 2013-05-09 End Date: 2021-05-08
Estimated potential lifetime emission reductions or sequestration: 196,720 t CO2e Estimated potential annual emission reductions or sequestration: 24,611 t CO2 e
Serial Number Vintage Year Company Name Status Quantity
(t CO2 e)
9327-1871-000-029-906-075 to 9327-1871-000-029-933-907 2018 CP Energy Marketing L.P. Registered (Others) 27,833
9327-1871-000-029-933-908 to 9327-1871-000-029-937-342 2018 ENMAX Energy Corporation Registered (Others) 3,435
9327-1871-000-012-462-345 to 9327-1871-000-012-478-731 2014 TransCanada Energy Ltd. Removed 16,387
9327-1871-000-012-443-138 to 9327-1871-000-012-448-723 2013 TransCanada Energy Ltd. Removed 5,586
9327-1871-000-025-109-879 to 9327-1871-000-025-134-160 2017 ConocoPhillips Canada Resources Corp. Pending Retirement 24,282
9327-1871-000-025-134-161 to 9327-1871-000-025-141-535 2017 ConocoPhillips Canada Resources Corp. Pending Retirement 7,375
9327-1871-000-021-559-704 to 9327-1871-000-021-585-742 2016 ConocoPhillips Canada Resources Corp. Pending Retirement 26,039
9327-1871-000-017-209-788 to 9327-1871-000-017-229-957 2015 Alberta Power (2000) Ltd. Pending Retirement 20,170
9327-1871-000-012-478-732 to 9327-1871-000-012-495-890 2014 Capital Power LP Pending Retirement 17,159
9327-1871-000-012-448-724 to 9327-1871-000-012-462-344 2013 Capital Power LP Pending Retirement 13,621
Total Serialized emission offsets for this project that have been Registered (Other): 31,268 , Removed: 21,973 , Pending Retirement: 108,646

Additional Credits

Serial Number Vintage Year Company Name Status Quantity
(t CO2 e)
There are no emission offsets for this project that have been serialized. Please contact the project developer or authorized project contact.
Disclaimer